Width of asphalt road
3,6m – 5,2m
With this sub-project is planned reconstruction of the existing asphalt road, parking place and sidewalks
With the reconstruction are planned the next activities:
- Marking the route of new planned sub – project
- Scratching the existing layer of asphalt
- Leveling, planning and compacting the subgrade until needed.
- Leveling and compacting the base course with crushed stone until needed
- Drainage with two line grids with channel and sediment
- Constructing predicted layers of asphalt
- Bituminized asphalt layer BNS 16a -6,0sm
- Spraying with bituminized emulsion in between the layers.
- Installation of granite curbs 18 / 10cm on a concrete base, according to detail
- Making a 10 cm concrete base for stacking stone slabs 10. Installation of broken stone slabs with a thickness of 3-5 cm for sidewalks
- Leveling the existing manholes