Reconstruction of the intersection of Sremski Front Street and Boris Kreiger

With this sub-project is planned reconstruction of the existing asphalt road (crossroad) and sidewalks.

With the reconstruction are planned the next activities:

  1. Marking the route of new planned sub – project
  2. Removing the existing damaged asphalt road, the existing base course and part of the subgrade.
  3. Leveling, planning and compacting the subgrade until needed.
  4. Leveling and compacting the base course with crushed stone until needed.
  5. Constructing predicted layers of asphalt
    1. Bituminized asphalt layer BNS 22 -12,0sm
    2. Layer of AB 11 – 4sm
  6. Spraying with bituminized emulsion in between the layers.
  7. Installing curb/edge concrete elements
  8. Constructing sidewalks with paver elements.
  9. Leveling the existing manholes
  10. Constructing pipes for drainage the storm water.
  11. Electrical installations.
  12. Mapping with horizontal and vertical signalization

Reconstruction of local street Panche Karagjozov

With this sub-project is planned reconstruction of the existing asphalt road and sidewalks.

With the reconstruction are planned the next activities:

  1. Marking the route of new planned sub – project
  2. Removing the existing damaged asphalt road, the existing base course and part of the subgrade.
  3. Leveling, planning and compacting the subgrade until needed.
  4. Leveling and compacting the base course with crushed stone until needed.
  5. Constructing predicted layers of asphalt
    1. Bituminized asphalt layer BNS 22 -7,0sm
    2. Layer of AB 11 – 4sm
  6. Spraying with bituminized emulsion in between the layers.
  7. Installing curb/edge concrete elements
  8. Constructing sidewalks with paver elements.
  9. Leveling the existing manholes
  10. Constructing pipes for drainage the storm water.
  11. Installing pipes for fiber optic cable.
  12. Mapping with horizontal and vertical signalization