Local Street from the river Treska to the City Cementery

With this sub-project is planned reconstruction of the existing dirt road. With the reconstruction are planned the next activities:

  1. Marking the route from the surveyor from the new planned sub – project.
  2. Leveling, planning and compacting the subgrade until needed.
  3. Constructing two layers of asphalt
    • binder course
    • wearing course
  4. Spraying with bituminized emulsion in between the layers.
  5. Installing pipes for optical cable
  6.  Mapping with horizontal and vertical signalization