Reconstruction of local road Rade Kratovche

With this sub-project is planned reconstruction of the existing asphalt road, and sidewalks

With the reconstruction are planned the next activities:

  1. Marking the route of new planned sub – project
  2. Scratching the existing layer of asphalt
  3. Leveling, planning and compacting the subgrade until needed.
  4. Leveling and compacting the base course with crushed stone until needed
  5. Constructing predicted layers of asphalt
    1. Bituminized asphalt layer BNS 16a -5,0sm
  6. Spraying with bituminized emulsion in between the layers.
  7. Installing curb/edge concrete elements
  8. Constructing sidewalks with paver elements.
  9. Leveling the existing manholes
  10. Mapping with horizontal and vertical signalization

Reconstruction of local street Gosho Vikentov

With this sub-project is planned reconstruction of the existing asphalt road, and sidewalks

With the reconstruction are planned the next activities:

  1. Marking the route of new planned sub – project
  2. Scratching the existing layer of asphalt
  3. Leveling, planning and compacting the subgrade until needed.
  4. Leveling and compacting the base course with crushed stone until needed
  5. Constructing predicted layers of asphalt
    1. Bituminized asphalt layer BNS 16a -4,5sm
  6. Spraying with bituminized emulsion in between the layers.
  7. Installing curb/edge concrete elements
  8. Constructing sidewalks with paver elements.
  9. Leveling the existing manholes
  10. Mapping with horizontal and vertical signalization.

Rehabilitation of the left carriage way of the 4-lane street Todosija Paunov

With this sub-project is planned reconstruction of the existing part of the road – the wearing course and the sidewalk. With the reconstruction are planned the next activities:

  1. Marking the route of the new planned sub – project.
  2. Scratching the existing wearing course.
  3. Leveling, planning and compacting subgrade until needed.
  4. Leveling and compacting base course with crushed stone until needed.
  5. Constructing two layers of asphalt:
    • binder course
    • wearing course
  6. Spraying with bituminized emulsion in between the layers.
  7. Reconstruction of the existing sidewalk with paver elements.
  8. Installing a curb/edge concrete element.
  9. Leveling the existing manholes.
  10. Mapping with horizontal and vertical signalization