Reconstruction of local street Pariska

With this sub-project is planned reconstruction of the existing part of the asphalt road – the wearing course and the existing sidewalks. With the reconstruction are planned the next activities:

  1. Marking the route of new planned sub – project
  2. Scratching the existing wearing course.
  3. Leveling, planning and compacting the subgrade until needed.
  4. Leveling and compacting the base course with crushed stone until needed
  5. Constructing two layers of asphalt
    • binder course
    • wearing course
  6. Spraying with bituminized emulsion in between the layers.
  7. Installing a curb/edge concrete elements
  8. Reconstructing the existing sidewalks with paver elements.
  9. Leveling the existing manholes
  10. Installing pipes for optical cable
  11. Mapping with horizontal and vertical signalization