Reconstruction of street Zapaden Bulevar

With this sub-project is planned reconstruction of the existing asphalt road.

With the reconstruction are planned the next activities:

  1. Marking the route of new planned sub – project
  2. Scratching the existing layer of asphalt
  3. Leveling, planning and compacting the subgrade until needed.
  4. Leveling and compacting the base course with crushed stone until needed
  5. Constructing predicted layers of asphalt
    1. Bituminized asphalt layer BNS 22cA-8,0sm
    2. Layer of AB 11c – 5,0sm
  6. Spraying with bituminized emulsion in between the layers.
  7. Installing curb/edge concrete elements
  8. Leveling the existing manholes
  9. Mapping with horizontal and vertical signalization.

Reconstruction of street Disanska

With this sub-project is planned reconstruction of the existing asphalt road and sidewalk.

With the reconstruction are planned the next activities:

  1. Marking the route of new planned sub – project
  2. Scratching the existing layer of asphalt.
  3. Leveling, planning and compacting the subgrade until needed.
  4. Leveling and compacting the base course with crushed stone until needed
  5. Constructing predicted layers of asphalt
    1. Bituminized asphalt layer BNS 22cA-8,0sm
    2. Layer of AB 11c – 5,0sm
  6. Spraying with bituminized emulsion in between the layers.
  7. Installing curb/edge concrete elements
  8. Leveling the existing manholes
  9. Constructing sidewalks with paver elements.
  10. Mapping with horizontal and vertical signalization

Reconstruction of street Ilindenska

With this sub-project is planned reconstruction of the existing asphalt road and part of the street sidewalks. With the reconstruction are planned the next activities:

  1. Removing the existing surface course, the existing base course and part of the subgrade, removing the existing sidewalks.
  2. Marking the route from the surveyor from the new planned sub – project.
  3. Leveling, planning and compacting the subgrade until needed.
  4. Leveling and compacting the base course with crushed stone until needed.
  5. Constructing two layers of asphalt:
    • binder course
    • wearing course
  6. Spraying with emulsion in between the layers.
  7. Installing a curb/edge concrete element.
  8. Reconstruction of existing sidewalks with paver elements.
  9. Leveling the existing manholes.
  10. Installing pipes for optical cable.
  11. Mapping with horizontal and vertical signalization.

Reconstruction of street Pionerska

With this sub-project is planned reconstruction of the existing asphalt road. With the reconstruction are planned the next activities:

  1. Marking the route of the new planned sub – project.
  2. Scratching the existing wearing course.
  3. Leveling, planning and compacting the subgrade until needed.
  4. Leveling and compacting the base course with crushed stone until needed.
  5. Constructing two layers of asphalt:
    • binder course
    • wearing course
  6. Spraying with bituminized emulsion in between the layers.
  7. Installing a curb/edge concrete element.
  8. Leveling the existing manholes.
  9. Installing pipes for optical cable.
  10.  Mapping with horizontal and vertical signalization.

Reconstruction of street Brakja Dzunovi

With this sub-project is planned reconstruction of  the existing  asphalt road.With the reconstruction are planned the next activities:

  1. Marking the route of the new planned sub – project
  2. Scratching the existing wearing course.
  3. Leveling, planning and compacting the subgrade until needed.
  4. Leveling and compacting the base course with crushed stone until needed
  5. Constructing two layers of asphalt
    • binder course
    • wearing course
  6. Spraying with bituminized emulsion in between the layers.
  7. Installing a curb/edge concrete elements
  8. Leveling the existing manholes
  9. Installing pipes for optical cable
  10. Mapping with horizontal and vertical signalization