With this sub-project is planned reconstruction of the existing asphalt road, building a new sidewalk(one side). With the reconstruction are planned the next activities:
- Removing the existing surface course, the existing base course and part of the subgrade, removing the existing sidewalks.
- Marking the route of the new planned sub – project.
- Leveling, planning and compacting subgrade until needed.
- Leveling and compacting the base course with crushed stone until needed
- Constructing two layers of asphalt
- binder course
- wearing course
- Spraying with bituminized emulsion in between the layers.
- Installing a curb/edge concrete elements
- Constructing a new sidewalk with paver elements.
- Leveling the existing manholes
- Installing pipes for optical cable
- Mapping with horizontal and vertical signalization