With this sub-project is planned reconstruction of the existing asphalt road and the sidewalks
With the reconstruction are planned the next activities:
- Marking the route of new planned sub – project
- Scratching the existing layer of asphalt
- Leveling, planning and compacting the subgrade until needed.
- Leveling and compacting the base course with crushed stone until needed
- Constructing predicted layers of asphalt
- Bituminized asphalt layer BNS 16 -7sm
- Spraying with bituminized emulsion in between the layers.
- Installing curb/edge concrete elements
- Reconstructing the existing sidewalk with paver elements.
- Leveling the existing manholes, constructing surface channel, pipes for drainage the storm water to the recipient
- Mapping with horizontal and vertical signalization
- Electrical installations (according to project for electrical installations)
With this sub-project is planned reconstruction of the existing road and building new sidewalks. With the reconstruction are planned the next activities:
- Removing the existing earth surface
- Marking the route from the surveyor from the new planned sub – project.
- Leveling, planning and compacting the subgrade until needed.
- Leveling and compacting the base course with crushed stone until needed
- Constructing one layer of asphalt
- Installing a curb/edge concrete elements
- Constructing new sidewalks with paver elements.
- Leveling the existing manholes
- Installing electricity and pipes for optical cable
- Mapping with horizontal and vertical signalization
With this sub-project is planned reconstruction of the existing dirt road. With the reconstruction are planned the next activities:
- Removing the existing dirt surface
- Marking the route of the new planned sub – project.
- Leveling, planning and compacting the subgrade until needed.
- Leveling and compacting the base course with crushed stone until needed
- Constructing one layer of asphalt
- Installing a curb/edge concrete elements
- Constructing new sidewalks, reconstruction and extending the existing ones.
- Leveling the existing manholes
- Installing electricity and pipes for optical cable
- Mapping with horizontal and vertical signalization
With this sub-project is planned reconstruction of the existing asphalt road. With the reconstruction are planned the next activities:
- Removing the existing earth surface
- Marking the route from the surveyor from the new planned sub – project.
- Leveling, planning and compacting the subgrade until needed.
- Leveling and compacting the base course with crushed stone until needed
- Constructing one layer of asphalt
- Installing a curb/edge concrete elements
- Leveling the existing manholes
- Installing electricity and pipes for optical cable
- Mapping with horizontal and vertical signalization
With this sub-project is planned reconstruction of the existing earth road and building new sidewalks. With the reconstruction are planned the next activities:
- Removing the existing earth surface
- Marking the route from the surveyor from the new planned sub – project.
- Leveling, planning and compacting the subgrade until needed.
- Leveling and compacting the base course with crushed stone until needed
- Constructing one layer of asphalt
- Installing a curb/edge concrete elements
- Constructing new sidewalks, reconstruction and extending the existing ones.
- Leveling the existing manholes
- Installing electricity and pipes for optical cable
- Mapping with horizontal and vertical signalization
With this sub-project is planned reconstruction of the existing asphalt road. With the reconstruction are planned the next activities:
- Removing the existing dirt layer.
- Marking the route of the new planned sub – project.
- Leveling, planning and compacting the subgrade until needed.
- Leveling and compacting the base course with crushed stone until needed
- Constructing one layer of asphalt
- Installing a curb/edge concrete elements
- Constructing new sidewalks, reconstruction and extending the existing ones.
- Leveling the existing manholes
- Installing electricity and pipes for optical cable
- Mapping with horizontal and vertical signalization
With this sub-project is planned reconstruction of the existing dirt road. With the reconstruction are planned the next activities:
- Removing the existing dirt surface
- Marking the route of the new planned sub – project.
- Leveling, planning and compacting the subgrade until needed.
- Leveling and compacting the base course with crushed stone until needed
- Constructing one layer of asphalt
- Installing a curb/edge concrete elements
- Leveling the existing manholes
- Installing electricity and pipes for optical cable
- Mapping with horizontal and vertical signalization