Rehabilitation of the left carriage way of the 4-lane street Todosija Paunov

Active
Budget

7843832.68mkd

Length

955.39

Width of asphalt road

7,0m

Sidewalks (one side)

2,5m - 5,0m

With this sub-project is planned reconstruction of the existing part of the road – the wearing course and the sidewalk. With the reconstruction are planned the next activities:

  1. Marking the route of the new planned sub – project.
  2. Scratching the existing wearing course.
  3. Leveling, planning and compacting subgrade until needed.
  4. Leveling and compacting base course with crushed stone until needed.
  5. Constructing two layers of asphalt:
    • binder course
    • wearing course
  6. Spraying with bituminized emulsion in between the layers.
  7. Reconstruction of the existing sidewalk with paver elements.
  8. Installing a curb/edge concrete element.
  9. Leveling the existing manholes.
  10. Mapping with horizontal and vertical signalization