Active
Width of asphalt road
3,5m
With this sub-project is planned reconstruction of the existing asphalt / dirt road. With the reconstruction are planned the next activities:
- Marking the route of the new planned sub – project.
- Removing the existing asphalt and dirt.
- Leveling, planning and compacting the subgrade until needed.
- Leveling and compacting the base course with crushed stone until needed.
- Constructing one layer of asphalt:
- Installing pipes for optical cable.
- Constructing surface concrete channels and access culvert for drainage the storm water to the recipient.