Active
Sidewalks (two sides)
0,5m – 1,8m
With this sub-project is planned reconstruction of the existing road and building new sidewalks. With the reconstruction are planned the next activities:
- Removing the existing earth surface
- Marking the route from the surveyor from the new planned sub – project.
- Leveling, planning and compacting the subgrade until needed.
- Leveling and compacting the base course with crushed stone until needed
- Constructing one layer of asphalt
- Installing a curb/edge concrete elements
- Constructing new sidewalks with paver elements.
- Leveling the existing manholes
- Installing electricity and pipes for optical cable
- Mapping with horizontal and vertical signalization