Reconstruction of street Mirka Ginova – Bogdanci

Active
Budget

mkd

Length

135.80m

Width of asphalt road

5,0m

With this sub-project is planned reconstruction of the existing asphalt road. With the reconstruction are planned the next activities:

  1. Removing the existing earth surface
  2. Marking the route from the surveyor from the new planned sub – project.
  3. Leveling, planning and compacting the subgrade until needed.
  4. Leveling and compacting the base course with crushed stone until needed
  5. Constructing one layer of asphalt
    • wearing course
  6. Installing a curb/edge concrete elements
  7. Leveling the existing manholes
  8. Installing electricity and pipes for optical cable
  9. Mapping with horizontal and vertical signalization