Width of asphalt road
12,0m
With this sub-project is planned reconstruction of the existing asphalt road.
With the reconstruction are planned the next activities:
- Marking the route of new planned sub – project
- Scratching the existing layer of asphalt
- Leveling, planning and compacting the subgrade until needed.
- Leveling and compacting the base course with crushed stone until needed
- Constructing predicted layers of asphalt
- Bituminized asphalt layer BNS 22cA-8,0sm
- Layer of AB 11c – 5,0sm
- Spraying with bituminized emulsion in between the layers.
- Installing curb/edge concrete elements
- Leveling the existing manholes
- Mapping with horizontal and vertical signalization.