Satelite view

Reconstruction of street Zapaden Bulevar

Active
Budget

8861620mkd

Length

609.00m

Width of asphalt road

12,0m

With this sub-project is planned reconstruction of the existing asphalt road.

With the reconstruction are planned the next activities:

  1. Marking the route of new planned sub – project
  2. Scratching the existing layer of asphalt
  3. Leveling, planning and compacting the subgrade until needed.
  4. Leveling and compacting the base course with crushed stone until needed
  5. Constructing predicted layers of asphalt
    1. Bituminized asphalt layer BNS 22cA-8,0sm
    2. Layer of AB 11c – 5,0sm
  6. Spraying with bituminized emulsion in between the layers.
  7. Installing curb/edge concrete elements
  8. Leveling the existing manholes
  9. Mapping with horizontal and vertical signalization.