Width of asphalt road
6,0m
With this sub-project is planned reconstruction of the existing asphalt road.With the reconstruction are planned the next activities:
- Marking the route of the new planned sub – project
- Scratching the existing wearing course.
- Leveling, planning and compacting the subgrade until needed.
- Leveling and compacting the base course with crushed stone until needed
- Constructing two layers of asphalt
- binder course
- wearing course
- Spraying with bituminized emulsion in between the layers.
- Installing a curb/edge concrete elements
- Leveling the existing manholes
- Installing pipes for optical cable
- Mapping with horizontal and vertical signalization