Width of asphalt road
3,5 to 4,0m
With this sub-project is planned reconstruction of the existing asphalt road. With the reconstruction are planned the next activities:
- Removing the existing dirt layer.
- Marking the route of the new planned sub – project.
- Leveling, planning and compacting the subgrade until needed.
- Leveling and compacting the base course with crushed stone until needed
- Constructing one layer of asphalt
- Installing a curb/edge concrete elements
- Constructing new sidewalks, reconstruction and extending the existing ones.
- Leveling the existing manholes
- Installing electricity and pipes for optical cable