Satelite view

Reconstruction of local street 11 October

Active
Budget

3495256mkd

Length

158.00m

Width of existing dirt road

4,5m- 5,5m

Sidewalk (one side)

1 x 1,5m


Width of new planned asphalt road

5,5m

Rigola one side

1 x 50cm

With this sub-project is planned reconstruction of the existing dirt road and constructing a new sidewalk.

With the reconstruction are planned the next activities:

  1. Marking the route of new planned sub – project
  2. Removing the existing dirt layer, the existing base course and part of the subgrade.
  3. Leveling, planning and compacting the subgrade until needed.
  4. Leveling and compacting the base course with crushed stone until needed.
  5. Constructing predicted layers of asphalt
    1. Bituminized asphalt layer BNS 16 – 8sm
  6. Installing curb/edge concrete elements
  7. Constructing sidewalk with paver elements.
  8. Mapping with horizontal and vertical signalization.

Gallery

Situation

Before the start of construction works
After competition of construction works

Documents