Active
Street Orce Nikolov - Width
6,0m
Sidewalk (two sides)
2 x 2,0m
Street Skopska - Width
5,5m
Sidewalk (two sided)
2 x 1,5m
With this sub-project is planned reconstruction of the existing asphalt road and sidewalk.
With the reconstruction are planned the next activities:
- Marking the route of new planned sub – project
- Removing the existing damaged asphalt road, the existing base course and part of the subgrade.
- Leveling, planning and compacting the subgrade until needed.
- Leveling and compacting the base course with crushed stone until needed.
- Constructing predicted layers of asphalt
- Layer of AB 11 – 5,0sm
- Installing curb/edge concrete elements
- Leveling the existing manholes.
- Constructing sidewalk with paver elements.
- Mapping with horizontal and vertical