Reconstruction of local street Zivko Firfov

Active
Budget

25899080.8mkd

Length

876.00 m

Width of asphalt road

7,0m

Existing sidewalks (two sided)

876.00 m

With this sub-project is planned reconstruction of the existing asphalt road, and extending sidewalks. With the reconstruction are planned the next activities:

  1. Removing the existing surface course, the base course, part of the subgrade and removing the existing sidewalks.
  2. Marking the route of the new planned sub – project.
  3. Leveling, planning and compacting the subgrade until needed.
  4. Leveling and compacting the base course with crushed stone until needed
  5. Constructing two layers of asphalt
    • binder course
    • wearing course
  6. Spraying with bituminized emulsion in between the layers.
  7. Installing a curb/ edge concrete elements
  8. Reconstructing the existing sidewalks with paver elements.
  9. Leveling the existing manholes
  10. Installing pipes for optical cable
  11. Mapping with horizontal and vertical signalization