Satelite view

Reconstruction of local street Goce Delchev – Demir Kapija

Active
Budget

2335874mkd

Length

213.00m

Width of existing dirt road

4,5m

Sidewalk (two sides)

2 x 1,0m


Width of new planned asphalt road

4,5m

With this sub-project is planned reconstruction of the existing dirt road and constructing new sidewalks.

With the reconstruction are planned the next activities:

  1. Marking the route of new planned sub – project
  2. Removing the existing dirt layer, the existing base course and part of the subgrade.
  3. Leveling, planning and compacting the subgrade until needed.
  4. Leveling and compacting the base course with crushed stone until needed.
  5. Constructing predicted layers of asphalt
    1. Bituminized asphalt layer BNS 16 – 8sm
  6. Installing curb/edge concrete elements
  7. Leveling the existing manholes and constructing new where needed.
  8. Constructing sidewalks with paver elements.
  9. Installing pipes for fiber optic cable.
  10. Mapping with horizontal and vertical signalization.

Gallery

Situation

Before the start of construction works
After competition of construction works

Documents

GRIEVANCE REDRESS MECHANISM

file a complaint