Active
Width of asphalt road
3,5m
Haunching (two sides)
2x0,50m
With this sub-project is planned reconstruction of the existing dirt road and constructing new sidewalks.
With the reconstruction are planned the next activities:
- Marking the route of new planned sub – project
- Removing the existing dirt layer, the existing base course and part of the subgrade.
- Leveling, planning and compacting the subgrade until needed.
- Leveling and compacting the base course with crushed stone until needed.
- Constructing predicted layers of asphalt
- Bituminized asphalt layer BNS 16 – 7sm
- Side – hunching for road stabilization
- Constructing side earth channel for drainage the storm water to the recipient.
- Constructing concrete access culverts.
- Mapping with horizontal and vertical signalization.