Active
With this sub-project is planned reconstruction of the existing dirt road and sidewalks.
With the reconstruction are planned the next activities:
- Marking the route of new planned sub – project
- 2 Removing the existing dirt layer.
- Leveling, planning and compacting the subgrade until needed.
- Leveling and compacting the base course with crushed stone until needed
- Constructing predicted layers of asphalt
- Bituminized asphalt layer BNS 16a – 7,0 sm
- Installing contrite gutter water cannels
- 7. Mapping with horizontal and vertical signalization.