Active
Width of existing dirt road
3,0m
Haunching two sides
60-75cm
Width of new planned asphalt road
4,0m
With this sub-project is planned reconstruction of the existing dirt road.
With the reconstruction are planned the next activities:
- Marking the route of new planned sub – project
- Removing the existing dirt layer, the existing base course and part of the subgrade.
- Leveling, planning and compacting the subgrade until needed.
- Leveling and compacting the base course with crushed stone until needed.
- Constructing predicted layers of asphalt
- Bituminized asphalt layer BNS 16a -7sm
- Installing curb/edge concrete elements
- Constructing concrete access culvert.
- Mapping with horizontal and vertical signalization.