Access Road – Street no.532 – Ilinden Municipality

Active
Budget

27551330mkd

Length

500m

Width of asphalt road

6,0m

Sidewalks (one side)

w=1,5m- l=1250m

With this sub-project is planned reconstruction of  the existing asphalt road, building a new sidewalk(one side). With the reconstruction are planned the next activities:

  1. Removing the existing surface course, the existing base course and part of the subgrade, removing the existing sidewalks.
  2. Marking the route of the new planned sub – project.
  3. Leveling, planning and compacting subgrade until needed.
  4. Leveling and compacting the base course with crushed stone until needed
  5. Constructing two layers of asphalt
    • binder course
    • wearing course
  6. Spraying with bituminized emulsion in between the layers.
  7. Installing a curb/edge concrete elements
  8. Constructing a new sidewalk with paver elements.
  9. Leveling the existing manholes
  10. Installing pipes for optical cable
  11. Mapping with horizontal and vertical signalization

Gallery

“улица-бр.532”-во-општина-Илинден2

01-01-1970

“улица-бр.532”-во-општина-Илинден

01-01-1970

Situation

Before the start of construction works
After competition of construction works

GRIEVANCE REDRESS MECHANISM

file a complaint